Timber is some most common material used for formwork. The problem of wooden formwork is every possibility of warping, swelling, also shrinkage of the timber.
It is not liable to shrinkage or distortion. However, steel formwork is comparatively more costly.
Requirements of Form Work
Good formwork should satisfy the following requirements
The material of some formwork should be cheap also it should be suitable during re-use several times.
This should do practically waterproof so that it does not absorb water of concrete. Also, its shrinkage and swelling should be minimal.
It should be strong enough to withstand all loads coming on it, such as a dead load of concrete and live load during its pouring, compaction, and curing.
The hydrostatic pressure of the fluid concrete acting against the vertical or inclined faces of form, and
Impact due to pouring concrete.
The temporary live loads of workmen and equipment, including the impact, may be taken equal to 3700 N/m2 for the design of planks and joints in bending and shear.
The hydrostatic pressure due to fluidity of concrete in the initial stages of pouring depends upon several factors such as a quantity of water in concrete, size of aggregates, rate of pouring and temperature.
Shuttering for Columns is Form Work
Shuttering during a column is presumably the simplest.
The boarding maybe 4 to 5 cm thick for walls up to 3 to 4 m high.
That boards are fixed to 5 x 10 cm posts, identified while studs, spaced on approximately 0.8 apart.
Horizontal walling of size 7.5 cm x 10 cm is fixed to the posts at a suitable interval.
The whole assembly is then strutted as shown, using 7.5 cm 10 cm struts. Some two shutters are kept alone equal over the thickness of the wall.
Each 15 mm plywood is commonly applied instead of boarding. The panels are erected in such a way that the lower panels can be removed when concrete is hard and used higher up the wall.
Framing of area 5 cm x 10 cm is applied to ply shutter. Some panels are fixed to a central including two end studs. The specific post consists of two pieces of timbers, 5 x 15 cm, blocked.
Formwork for stairs
Deck slabs are carried on cross-joists which are in turn supported on raking ledgers.